What permits do you need to open a contractor or trade in Fort Worth?
In short
A contractor or trade in Fort Worth, TX has 2 permits that apply to every business of this type, plus 10 more that depend on your premises, signage or how you are set up. City of Fort Worth Development Services charges $63 per reinspection for the reinspection fee. 6 of the 12 are charged as a range or formula rather than a flat fee. Verified 2026-08-24 against the issuing agencies’ published fee schedules.
The permits at a glance
| Permit | Issuing agency | Fee | Renews | Last checked |
|---|---|---|---|---|
| Commercial Building Permit | City of Fort Worth Development Services | $96.84 up to 30 sq ft; $96.84 plus $1.19 per additional sq ft to 400; $542.44 for the first 400 sq ft plus $0.89 per additional sq ft to 790, continuing on Table 1-C-1 | not stated in the published fee schedule | 2026-08-24 |
| Plan Review Depositonly if it applies to you | City of Fort Worth Development Services | $24.75–$276.75 by review route | one-time, per application | 2026-08-24 |
| Demolition and Moving Permitonly if it applies to you | City of Fort Worth Development Services | $84.37–$1,717.87 by floor area | not stated in the published fee schedule | 2026-08-24 |
| Annual Contractor Registration | City of Fort Worth Development Services | $168.75–$562.50 per year, by contractor class | one year | 2026-08-24 |
| Reinspection Feeonly if it applies to you | City of Fort Worth Development Services | $63 per reinspection | per inspection | 2026-08-24 |
| Fire Operational Permit — Hazardous Materialsonly if it applies to you | Fort Worth Fire Department | $390 per permit | not stated in the published fee schedule | 2026-08-24 |
| Fire Operational Permit — High-Piled Storageonly if it applies to you | Fort Worth Fire Department | $165 per permit | not stated in the published fee schedule | 2026-08-24 |
| Zoning Change Applicationonly if it applies to you | City of Fort Worth Development Services | $1,350 under 1 acre; $2,025 to 2 acres; $3,037.50 for 5.01-10 acres; $3,712.50 for 10.01-25 acres; above 25 acres $3,712.50 plus $84.37 per acre, capped at $10,125 | one-time, per application | 2026-08-24 |
| Planned Development Site Plan Reviewonly if it applies to you | City of Fort Worth Development Services | $900 base; $1,350 for 0-5 acres, $3,037.50 for 5.01-10 acres, $3,712.50 at 10 acres or more plus $84.37 per acre, capped at $10,125 | one-time, per application | 2026-08-24 |
| Certificate of Formationonly if it applies to you | Texas Secretary of State | $300 one-time filing | no expiry | 2026-08-20 |
| Electrical Contractor Licenceonly if it applies to you | Texas Department of Licensing and Regulation | $110 non-refundable application | annual | 2026-08-20 |
| Assumed Name Certificate (DBA)only if it applies to you | Texas Secretary of State | $25 one-time filing | up to ten years, renewable | 2026-08-21 |
Fees shown as a range or formula are set that way by the issuing agency — we do not average them into a single number.
How much does it actually cost to permit a contractor or trade in Fort Worth?
There is no single figure, and any site quoting one is rounding away the part that matters. Of the 12 records listed for a contractor or trade in Fort Worth, TX, 2 apply to every business of this type and 10 are conditional. Adding every fee on the page together would overstate what most operators pay, because it would include permits they never need.
6 of the 12 are charged as a range or a formula set by the issuing agency, and 0 have no fee published at all. The ones that vary:
Commercial Building Permit: $96.84 up to 30 sq ft; $96.84 plus $1.19 per additional sq ft to 400; $542.44 for the first 400 sq ft plus $0.89 per additional sq ft to 790, continuing on Table 1-C-1
Plan Review Deposit: $24.75–$276.75 by review route
Demolition and Moving Permit: $84.37–$1,717.87 by floor area
Annual Contractor Registration: $168.75–$562.50 per year, by contractor class
Zoning Change Application: $1,350 under 1 acre; $2,025 to 2 acres; $3,037.50 for 5.01-10 acres; $3,712.50 for 10.01-25 acres; above 25 acres $3,712.50 plus $84.37 per acre, capped at $10,125
Planned Development Site Plan Review: $900 base; $1,350 for 0-5 acres, $3,037.50 for 5.01-10 acres, $3,712.50 at 10 acres or more plus $84.37 per acre, capped at $10,125
Which offices issue these permits in Fort Worth?
Permits for a contractor or trade in Fort Worth, TX come from 4 separate offices: City of Fort Worth Development Services, Fort Worth Fire Department, Texas Secretary of State, Texas Department of Licensing and Regulation. No single office issues them all, which is why an opening means filing in several places rather than one.
Is anything about these requirements changing?
Fort Worth bands new commercial construction by square footage on Table 1-C-1, covering assembly, business, educational, high-hazard, institutional and mercantile use groups. Three fixed charges sit on every application regardless of size: a $31.50 permit application fee, a $16.87 technology fee, and $31.50 more if you file on paper rather than online. There is a real discount worth engineering for — where plan review is done by City staff but field inspections are carried out by an approved third party, the permit fee is multiplied by 0.55, a 45% reduction calculated to the penny.
$276.75 where the plans require circulation between departments and $106.87 where they do not; on the third-party review route the same two figures drop to $49.50 and $24.75. Choosing third-party review therefore cuts the deposit by roughly four fifths. No deposit is required for additions and remodels to existing Group R-3 occupancies or their accessory structures.
Banded by size: $84.37 up to 1,000 sq ft, $171.00 to 2,000, $319.50 to 3,000, $479.25 to 5,000, $642.37 to 10,000, $858.37 to 20,000, and $1,717.87 above 20,000 sq ft. Demolishing a structure 45 years or older carries an additional $56.25 — a heritage review trigger dressed as a fee, and worth checking the build date before programming a teardown.
$168.75 a year for a building or sign contractor and $562.50 for a parkway and utility contractor — over three times as much, reflecting the work in the public right of way. Sec. 118.2.1 requires every individual or business registering under the Code to pay the prescribed fee.
$63 a reinspection, and $63 an hour for any inspection with no fee otherwise specified, at a half-hour minimum. Inspections outside normal business hours are $112.50 and outside the city limits $94.50 an hour at a four-hour minimum. Plan revisions escalate steeply: the first is $63, the second $112.50, the third and fourth $225 each and the fifth and beyond $337.50 — against a flat $39.37 on the third-party route, which is the cheapest way through a project that is going to change more than twice.
$390 for hazardous materials and the same $390 for an HMM facility — jointly the most expensive operational permits Fort Worth issues, alongside a place of assembly above 1,000 occupants. Lumber yards and woodworking plants are $305. Flammable and combustible liquids are $110, cutting and welding $110, industrial ovens $110, and repair garages and motor fuel-dispensing facilities $110.
$165. The same $165 covers compressed gases, cryogenic fluids, LP-gas, amusement buildings, aviation facilities, explosives, magnesium, pyroxylin plastics, tire rebuilding plants, waste handling, and liquid or gas-fuelled vehicles inside assembly buildings. At the cheaper end, $80 covers hot work operations, spraying and dipping, combustible dust-producing operations, combustible fibres, energy storage systems, open flames and candles, organic coatings, cellulose nitrate film and miscellaneous combustible storage. Storage of scrap tyres is $60.
Banded by acreage and capped at $10,125. Two things are worth knowing before filing. The fee DOUBLES where double noticing and special City Council consideration are required or requested outside the normal processing schedule — and the ordinance is explicit that the doubled charge is not waived by any incentive programme the project qualifies for. And there is a genuine discount in the other direction: an application under one acre that down-zones to a one- or two-family district consistent with the adopted Comprehensive Plan is $506.25 rather than $1,350.
A planned development or conditional use permit carrying requested development standard waivers adds a waiver fee of $843.75. For a multi-family planned development the waiver charge is $675 for the first and $337.50 for each additional one. An administrative site plan amendment is $281.25. Conservation District and Historic and Cultural Landmarks District overlay rezonings carry no fee at all.
Required to form an LLC or corporation, not to trade as a sole proprietor. Texas has no statewide general business licence, so for many businesses this filing plus a sales and use tax permit is the entire state-level obligation.
Texas licenses no general contractor - there is no statewide builder licence. Individual trades are licensed instead: electrical, plumbing and HVAC, each under its own programme. The $110 is the application fee. Published renewal figures conflict between $110 and $165 depending on licence subtype, so no renewal amount is recorded until a reviewer confirms which applies.
Only needed if you trade under a name different from the one on your formation filing. The certificate is effective for a term not exceeding ten years from the date of filing and does not roll over by itself — it must be actively renewed, and a new certificate can be filed within six months of the original expiring. The $25 is the Secretary of State fee; sole proprietors and general partnerships file with the county clerk instead, at county rates.
Sources
Every figure above was read from one of these government pages on the date shown. Confirmed by Editorial Team.
- Development fees schedule — Ordinance No. 27191-09-2024 amending the Code of the City of Fort WorthCity of Fort Worth Development Services · primary source · retrieved 2026-08-24
- Formation of Texas Entities FAQs - Texas Secretary of StateTexas Secretary of State · primary source · retrieved 2026-08-22
- Apply for a New Electrical Contractor License - TDLRTexas Department of Licensing and Regulation · primary source · retrieved 2026-08-22
- Form 503 - Instructions for Assumed Name CertificateTexas Secretary of State · primary source · retrieved 2026-08-22
Related
- All permits in Fort Worth
- Contractors and trades — national overview
- Contractors and trades in Grand Prairie, TX
- Contractors and trades in Arlington, TX
- Contractors and trades in San Antonio, TX
- Contractors and trades in Pasadena, TX
- Contractors and trades in Abilene, TX